S/N | PROJECT TITLE AND DATES | CLIENT/ PARTNER | ULTIMATE CLIENT |
1 | ENGINEERING, PROCUREMENT AND CONSTRUCTION WORKS FOR PHASE-1 210MMSCFD PRESSURE REDUCTION AND METERING STATION GAS SUPPLY TO OMOTOSHO POWER PLANT, OMOTOSHO – 2008/2009 | G C PARSONS INTERNATIONAL LIMITED | NIGERIAN GAS COMPANY LIMITED |
2 | INSTALLATION AND COMMISSIONING OF 25MMSCFD NGC / GUINNESS PRESSURE REDUCTION AND METERING STATION, BENIN CITY. 2009 | GAS TECHNOLOGY RESOURCES, USA | GUINNESS NIGERIA PLC |
3 | E& I CONSTRUCTION, INSTALLATION AND COMMISSIONING OF 30MMSCFD PLATFORM PETROLEUM LIMITED LPG PLANT, UMUTU. 2010 | G C PARSONS INTERNATIONAL LIMITED | PLATFORM PETROLEUM LIMITED |
4 | INSTALLATION AND COMMISSIOING OF ABA NGC PRESSURE LET-DOWN STATION - 2011 | GC PARSONS / GAS TECHNOLOGY RESOURCES | NGC |
5 | E& I INSTALLATION AND COMMISSIONING WORKS FOR 200MMSCF PRESSURE REDUCTION AND METERING STATION GAS SUPPLY TO MAPUTO POWER PLANT, MAPUTO, MOZAMBIQUE. - 2013 | ZENNERGY INTERNATIONAL UK. | MAPUTO GAS, MOZAMBIQUE |
6 | ELECTRICAL AND INSTRUMENTATION WORKS FOR ABITEYE AND ESCRAVOS 16” PIG LAUNCHER AND RECEIVER - 2013 | HOMIK ENGINEERING / FENOG NIGERIA LIMITED | CHEVRON NIGERIA LIMITED |
7 | EPC – ENGINEERING PROCUREMENT INSTALLATION AND COMMISSIONING OF 60MMSCFD METERING SYSTEMS AND GAS SUPPLY TO NDPHC, OBOB, OMOKU - 2013 -2014 | HOMIK ENGINEERING / FENOG NIGERIA LIMITED | NIGERIA AGIP OIL COMPANY |
8 | INSTALLATION AND COMMISSIONING OF 30MMSCFD PRESSURE REDUCTION AND METERING STATION OF GAS SUPPLY TO BN CERAMICS, AJAOKUTA, KOGI STATE -2015 | BABLINK RESOURCES NIG LIMITED | NIGERIAN GAS COMPANY LIMITED |
9 | REACTIVATION AND COMMISSIONING OF FPSO BOILER AT SEPCOL FPSO - 2016 | SEPCOL | SEPCOL |
10 | E&I INSTALLATION WORKS ON 50MMSCF PRMS OF GOODWILL CERAMICS COMPANY, TANZANIA 2017 | ZENNERGY INTERNATIONAL | TANZANIA PETROLEUM DEVELOPMENT COMPANY |
11 | INSTALLATION AND COMMISSIONING OF EGBIN NGC VOLUMETRIC FLOW CONTROL SYSTEM 2017 | BABLINK RESOURCES NIG LIMITED | NIGERIAN GAS COMPANY LIMITED |
12 | COMPLETION OF ASSEMBLY OF 5NOS 10MMSCFD CUSTOMER PRMS, OTA - 2017 | ZENNERGY WEST AFRICA LIMITED | SHELL NIGERIAGAS, OTA |
13 | INSTALLATION AND COMMISSIONING OF FLOW COMPUTER/ METERING ON OEECL GAS SKID | OEECL | OEECL, OMOTOSHO |
14 | INSTALLATION AND COMMISSIONING OF GEREGU NGC VOLUMETRIC FLOW CONTROL SYSTEM - 2018 | BABLINK RESOURCES NIG LIMITED | NIGERIAN GAS COMPANY LIMITED |
15 | COMPLETION OF ASSEMBLY OF 8NOS 10MMSCFD CUSTOMER PRMS, OTA - 2018 | ZENNERGY WEST AFRICA LIMITED | SHELL NIGERIAGAS, OTA |
16 | COMMISSIONING OF GLYCOL REBOILER AND REGENERATION UNIT, KUWAIT 2019 | GAS TECHNOLOGY RSOURCES, USA | SPETCO, KUWAIT |
Finally, PASSPOSSIBLE LIMITED LTD desire to have a cordial business relationship with your organization and we will consider it an honor if PASSPOSSIBLE LIMITED LTD is favorably considered for the patronage sought. We are at your disposal for further clarifications on related matters.
Gallery

COMMISSIONING OF FW MURPHY CONTROL PANEL OF UTOROGU CRUDE OIL PUMP

INSTALLATION OF HEATER AT PLATFORM PETROLEUM LIMITED GAS PLANT, UMUTU

AFTER SUCCESSFUL COMMISSIOING OF CATERPILLAR ENGINGE OF UTOROGU CRUDE OIL PUMP

MAINTENANCE AND REPAIR OF BOILER PRESSURISATION UNIT AT IHOVBOR NGC PRMS STATION

INSTALLATION OF HEATER AT PPL UMUTU

COMMISSIOING OF TURBINE METER AND VOLUME CORRECTOR AT GOODWILL CERAMICS PRMS, TANZANIA

AFTER SUCCESSFUL COMPLETION OF GOODWILL CERAMICS PRMS IN TANZANIA